LIG Huong Hoa 2 Wind Power Plant

Owner LICOGI 13 – INFRASTRUCTURE AND CONSTRUCTION INVESTMENT JOINT STOCK COMPANY
Voltage level
220kV
Capacity 48MW
Location Quang Tri province
Project LIG Huong Hoa 2 Wind Power Plant
Client
LICOGI 13 – INFRASTRUCTURE AND CONSTRUCTION INVESTMENT JOINT STOCK COMPANY
Tasks of Vietnam PRP Corp.
  1. Survey of Windpower plant part
  2. Survey of Substation and Transmission line part
  3. Feasibility Study And Basic Design
  4. Preparation and Acquirement of Agreements from EVN
  5. Preparation and Acquirement of Agreements/approvals from relevant authorities for Feasibility Study
  6. Feasibility Study (FS) and Basic Design for Substation and Transmission lines part; Wind Power Plant part
  7. Power Purchase Agreement (PPA)

LIG Huong Hoa 2 Wind Power Plant in Quang Tri province has a total capacity of 48MW.