Ia Pech 2 Wind power plant

Owner Dien xanh gia lai investment energy joint stock company
Voltage level
110kV
Capacity 50MW
Local
Gia Lai province
Project
Ia Pech 2 Wind power plant
Client
Dien xanh gia lai investment energy joint stock company
Our task
  1. All of agreement with EVN
    + Agreement on Technical Design of Grid connection points
    + Agreement on Relay protection and Automation system
    + Agreement on SCADA and Telecommunication system
    + Agreement on Tariff metering system
  2. Negotiating Power Purchase agreement with EVN

Ia Pech 2 wind power plant in Gia Lai province has a total capacity off 50MW. The power plant is connected to 110kV substation of the Ia Pech power plant